Environmental Mitigation Revetment Project Update

RMIPA’s Environmental Mitigation Revetment (EMR) Project, previously called the revetment project, is almost a year into its construction phase since the issuance of the Notice To Proceed. The main purpose of the project is to construct a new revetment wall along the existing lagoon coastline from the airport terminal eastward to the water reservoirs, as shown on the photo below.

EMR from above terminal comp

The area was unprotected prior to the implementation of the EMR project. The lack of revetment protection in the area has caused significant erosion due to sea level rise and other environmental factors, not to mention flooding of the existing road during kind tide events.

20150722_084323

Included in the project will be construction of public access ways over the revetment to the beach. This feature was added so that the public can have easy access to the beach. In addition, covered picnic facilities equipped with picnic tables, barbecue and refuse facilities, will also be constructed for the public’s use.

DSC02101

The contractor for the project is Pacific International Inc. and the construction management services is provided by Beca International Consultants. Ltd.

The current completion date of the EMR is June 2016.